Photo of the week

Photo of the week, June 26, 2024

A ground level look at the future Emergency Department entry, bonus points if you can spot the signed beam installed May 23rd!

june 19 24 pow.png

High level view of the future west entrance. 

jun 12 24 pow.png

The Inpatient Unit Tower has now officially exceeded the height of the Diagnostic & Treatment centre. 

pow jun 5 2024.png

Visible progress as the reach out takes shape, at lower left.

pow-may 29 2024.png
A project milestone celebrated on site with staff and community partners.
pow may-22-2024.png

Progress continues with the roof install for the top level of the Diagnostic and Treatment centre.pow may-15-2024.png
An updated view towards Swuq'us. pow may-8-2024.png
View from the North West corner with Somenos Lake shown in the distance.
pow may-1-2024.png
Project staff pose with D&T steel beam while celebrating staff and user groups at the current CDH. 
POW-apr-24- 2024.png

The Inpatient Unit continues its growth with level 5 started.pow-apr-17-2024.png

A look at the level one entry, on the East side. 
pow-april10-2024.png

Director of Indigenous engagement, Jennifer Jones, and Cowichan Tribes Chief Cindy Daniels, stand outside the future Emergency Department entrance. 
pow-apr-3-2024.png

North East Corner, with mechanical and electrical level visible at top. mar_27_2024.png

A high level view of the active build site, from the North West corner. 
mar-20-2024-pow.png

A look at future reach out and main entry from Bell McKinnon approach.
mar-13-pow.png
A ground level look at the future Emergency Department entrance. Mar 6th 2024 - POW (1).png

Visible progress and an active concrete pour captured at lower left.
Feb 28th 2024 - POW.png

A near reverse look from Bell McKinnon to Service Centre and Quonset at back. 
Feb 21 2024 - POW.png
Looking from the North East corner, towards Bell McKinnon Road. 
Feb 14th 2024 - POW.png
Ground level view, of the future Emergency Department approach from Bell McKinnon Road. 
Feb 7th 2024 - POW.png
Another perspective from high above the build site. 
Jan 31 2024 - POW.png
Aerial view from the South West corner. 

Jan 24th 2024 - POW.png

Visible growth from the same vantage captured on October 25th, 2023.

Jan 17th 2024 - POW.png

Shout out to the crew that doesn't quit! Showing up, even on the snowy days.
Jan 10th 2024 - POW.png

A beautiful start to the New Year as crews continue to build skyward. 
Dec 27 - POW.png

A ground level look at the North side.
Dec 20-POW (1).png

Crews continue work on both the service centre and main building as winter approaches. 

Dec 13-POW.png

Taking a look from above of both the Diagnostic and Treatment Centre and the Service Centre at far left. 
Dec 6 -POW.png
Another view of the impressive footprint and foundation. See if you are able to spot the two workers on top of level 3.
Nov 29-pow.png
Swuq'us provides a beautiful background to the sunlit site. 
Nov 22-pow.png
Overall site progress shown with Inpatient Unit and Diagnostic & Treatment Centre nearing finish of slab on grade work. 
Nov 15th-pow.png
Activity continues on site with many moving parts and materials. 
11.08.23.png

Take a peek through the clouds and cranes to the active construction site. 

1nov2023_pow.png

An overhead look to the entire site and surrounding forest on a sunny November day. 

Oct 25th-pow.png

A misty backdrop to the rising Diagnostic and Treatment centre offers a great scale to the incredible work underway. 

Oct 18th-pow.png

This week's photo takes a close look at Brodie, an ironworker on the project. 

Oct 11th-pow.png

This week's photo captures site staff Paolo, Jamie, Terre, and Romi, tending to the grounds while fully equipped in personal protective equipment. 

Oct 4th-pow.png

At the new CDH, site crews building the future hospital honoured National Day for Truth and Reconciliation. 

Sept 27-pow.png

This week's capture takes a close up look at the Diagnostic and Treatment centre as it continues its climb upwards. September 27, 2023.

Sept 20th-pow.png

Aerial site photo taken September 20, 2023

Sept 13-pow.png

Crane cam photo taken September 13, 2023.

Sept 6-pow.png

Crane cam photo taken September 6, 2023.

Aug29_2023_POW.png

Crane cam photo taken August 30, 2023.

Aug 23 POW-1170 × 412px.png

Crane cam photo taken August 23, 2023.

Aug 16 POW-1170 × 412px.png

Crane cam photo taken Aug 16, 2023

Aug 9 POW-1170 × 412px.png

Crane cam photo taken Aug 9, 2023

Aug2_CraneCam_POW.png

Crane cam photo taken Aug 2, 2023

July26_CraneCam_POW.png

Crane cam photo taken July 26, 2023

July19_CraneCam_POW.png

Crane Cam Photo taken July 19, 2023

July12_CraneCam_POW.png

Crane Cam Photo taken July 12, 2023

July5_CraneCam_POW.png

Crane Cam Photo taken July 5, 2023

June28_CraneCam_POW.png

Crane Cam Photo taken June 28, 2023

June21_CraneCam_POW.png

Crane Cam Photo taken June 21, 2023

June14_POW.png

Crane Cam Photo taken June 14, 2023

June 8 POW-1170 × 412px.png

Crane Cam photo taken June 8, 2023

June 1 POW-1170 × 412px.png

Crane Cam photo taken June 1, 2023

Revised May 24 POW-1170 × 412px.png

Crane Cam photo taken May 25, 2023

Revised May 17 - POW-1170 × 412px.png

Crane Cam photo taken May 17, 2023